PHOTOS - Page 4
Pages 1-8 are taken BEFORE the Liberty Homes, Inc set crew re-set the modular sections on March 10, 2006.
BELOW... the front boxed bay window is off center (follow the black vertical line I added). This is the way it was built at the Liberty factory.
BELOW... broken off areas and cracks in this window. This is how it was delivered.
BELOW... the end of the soffit & fascia is bent downward. This is how it was delivered.

BELOW... the siding is gapped severely away from the window.
BELOW... is the cracked window frame that was mentioned in the "Delivery Day" photo page. This window would have to be replaced also.
BELOW... a bent corner piece. This is trivial in relationship to the other items that are wrong. This is how it was delivered.

BELOW... the exterior faucet's seal is broken, and the screws are not holding it on. This is one on the broken water lines inside the home. It just rattles there because it is broken on the other side.